Daviess Co. Bridge Reconstruction

Daviess Co. Bridge Reconstruction

Oct

30

Author Icon

Ashlyn Halstead

Boost This Post

Boost Icon

Project Overview:

Our crews are hard at work in the town of Montgomery, Indiana where they are demolishing and replacing Daviess County Indiana Bridge 155 located on 3rd street over CSX Railroad. Along with the bridge work, we will bring in new concrete and bituminous pavement road will be constructed along a portion 3rd St. on both sides of Bridge 155 and new bituminous pavement along a portion of Railroad St. west of CR 650 E. Curbs, sidewalks, and storm sewers will all be installed as well.

Current Operations:

In the month of September, Brent Foster’s crews have completed the mainline concrete pavement, concrete railing on bridge, sidewalk at all locations off the bridge, curb and gutter and driveways. We have finished the riprap at pipe outlets. All grading is completed and mulched seeding was placed on all exposed areas. Stone drivers alone Railroad St were poured, and a surface seal/anti-graffiti coating was placed on all concrete areas. Bituminous pavement was laid at the planned locations on Railroad St. and 3rd St, along with the alley south of the bridge. As we continue this job, we plan for pavement marking and guardrail to go up. All remaining work will be completed this month with a target final completion date of November 30th. Stay tuned for a final update on our social media channels!

Milestone Social Media:

Facebook

A slide show of our hard-work so far! Great work crew!

Boost This Post

Boost Icon

Related Posts

Oct

1

From Building Roads to Preserving Icons: 30 Years of Milestone Contractors

This year, we proudly celebrate our 30th anniversary, marking three decades of growth, innovation and commitment to quality in the construction industry. A significant facet of who we are today is our long-standing relationship with the iconic Indianapolis Motor Speedway (IMS). This partnership has led to innovative pavement preservation strategies, ensuring the track remains in […]

Read More

Boost This Post

Boost Icon

Sep

26

Safety Excellence: Saluting Our Safety Champion Dan Silverman

Congratulations to Safety Champion, Dan Silverman. Dan was nominated for routinely going above and beyond when it comes to his personal safety and those of his co-workers.   Recently, Dan has been the paver operator on nights for a high-profile route on the US 30 job. Portions of this job called for the use of our […]

Read More

Boost This Post

Boost Icon

Sep

20

Building Better Connectivity One Road and Bridge at a Time

Our Milestone team has been working full steam ahead on Phase III of the Fullerton Pike Corridor Reconstruction Project. The project aims to provide east to west connectivity on the south side of Bloomington and ease traffic congestion on and off I-69 into the heart of Bloomington.  Previous phases on the reconstruction project began in […]

Read More

Boost This Post

Boost Icon